INSTRUCTIONS TO PROPONENTS

IP 6 - DELIVERY OF PROPOSAL

6.1    The properly completed and executed Proposal Form shall be enclosed only in the pre-addressed envelope provided
         by the Corporation. That envelope shall be sealed and must be actually delivered into the possession of the
         Corporation along with supporting technical material as required by IP 4, at the address given in the advertised
         Invitation for Proposal prior to the time and date specified there for the closing of Proposals. The name and address
         of the Proponent(s) and the project description must appear on the face of the supplied envelope.

6.2    Proposals and other related documents received after the advertised time and date of closing will not be considered
         by the Corporation.

IP 7 - REVISION OF PROPOSAL

7.1    A Proposal already delivered to the Corporation may only be revised in the manner described in IP 7.2 and to
         qualify, the revision must be actually received by the Corporation at the address given in the advertised Invitation
         for Proposal prior to the time and date specified there for the closing of Proposals. The revision must be plainly
         referable to a particular Proposal.

7.2    Revisions shall be submitted only by signed letter delivered or transmitted by facsimile machine to the number given
         on the Invitation for Proposal. Only the Proponent's entries on the delivered Proposal may be revised; the revision
         must state only the amount by which a figure is to be increased or decreased, or specific directions as to the
         exclusion or inclusion of particular words. Any revision which states the actual total amount of a Proposal
         will be rejected by the Corporation.

IP 8 - ACCEPTANCE OF PROPOSAL

8.1    The lowest or any Proposal will not necessarily be accepted.

8.2    In the event only one Proposal is received, the Corporation reserves the right to open this proposal without reference
         to the Proponent.

IP 9 - SCHEDULING OF WORK

         The successful proponent will provide a schedule for the completion of the work within 7 days after the Award of
         Contract.


[ Previous Page || Table of Contents || Overview || Section TOC || Next Page ]