NEW CONSTRUCTION - DIRECT BID SPECIFICATION

2.1              Instructions to Designers

                   This section is intended to give designers specific instructions as to how to structure the construction documents
                   using the British Columbia Buildings Corporation standardized documents found in Section 2.0.

2.1.1           Technical Requirements

2.1.1.1        Table of Contents - Prepare a Table of Contents following the headings below.

2.1.1.2        15910 Scope - Prepare an overview and explanation of the CCS objectives as they relate to this project. Note
                   any particular features or issues which may assist the controls contractor to understand the project better.

2.1.1.3        15920 Project Specific Alterations to BCBC - CCS Performance Specification -  This is where any
                   deviations to the BCBC standard CCS Performance Specification, Section 15940, can be made, if necessary.
                   This approach is used to assist the controls contractors in focusing on issues which may affect pricing of the
                   project.

2.1.1.4        15925 Sequence of Operation (if required) - This section is to be used if there are any strategies to be
                   programmed by the contractor which do not have standardized System Points Lists, Graphics & Start up Logic
                   prepared.  

2.1.1.5        15930 Systems (Points Lists, Graphics & Start Up Logic)
                  
Summary Page - Prepare a summary page of the points and graphics following the format in the example in
                   Section 10 (form 10_E5).
                   DDC Points - Choose the BCBC standardized System Points Lists, Graphic & Start Up Logic sheets from
                   Section 5 for each mechanical or electrical system. For more in-depth instruction see Section 5.1.
                   Misc. Points - Add these points on form 5_O2 found in Section 5.O.
                   Non DDC Points - Add these points on form 5_O3 found in Section 5.O.
                   Emergency/Safety Points - Add these points on form 5_O4 found in Section 5.O.
                   Other Graphics - Add any other graphics required. Where standardized graphics are not in manual, BCBC will
                   prepare same for the project in conjunction with the designer.

2.1.1.6        15940 BCBC - CCS Performance Specification - Section 2.3  - Attach this document unaltered.