[
Previous Page ||
Table of Contents ||
Overview ||
Section TOC ||
]
The information displayed here is available as a
Microsoft Word.doc file. Please click on this link to download this
file.
CCS: Performance Specifications Section 15940
PS 9 - SUBSTANTIAL PERFORMANCE TEST PROCEDURES
9.1 - Overview
- The successful completion of a SEVEN (7) day acceptance test as
described herein is a prerequisite to granting Substantial Performance. Before
the SEVEN (7)-day acceptance test may begin, the CCS must be completely
operational including the following:
- .1 - Every point shall be checked end to end to ensure accuracy and integrity of
systems and be signed off by the Contractor and the Owner.
- .2 - Operating Code shall be written in Operator Control Language (OCL)
and successfully control the systems.
- .3 - Time schedules shall be built and in control of time-controlled
equipment.
- .4 - Graphic displays (when provided), must be installed and fully operational for each graphic
screen page.
- .5 - Each control loop measured variable, controlled variable and set point if
calculated, shall be placed on a FIFTEEN (15)- minute continuous trend for at
least TWENTY-FOUR (24) hours to prove stability of loop.
- .6 - Each space sensor shall be placed on a THREE (3)-hour trend for One Hundred
(100) samples.
- .7 - Runtime totalizer shall be set on all digital outputs.
- .8 - Load/save of panel programs must be demonstrated.
- .9 - All features of system shall have been exercised.
- .10 - Operator shall have been briefed on operation of system.
- .11 - A trend on one panel shall be set up for a point from every other panel.
These points shall also be trended in their own panels for the same intervals.
Comparison of the two groups of trends will indicate if any communication
problems are occurring during the SEVEN (7)-day test.
- .12 - All alarms shall be operational.
- .13 - Calibration of all sensors.
9.2 - During SEVEN (7)-Day Test
- .1 - Fire alarm shall be activated to ensure correct action of all fire
and smoke sequences.
- .2 - Power failure for building shall be simulated and system recovery
monitored.
- .3 - System must be available for Corporation's representative to exercise most
features of the system.
- .4 - Demonstration of modem operation will be required. All functions of the
CCS shall be accessed through the modem to prove operation.
- .5 - Demonstration of hardware low limits and damper interlocks will be
required.
- .6 - Spot checks of points end-to-end integrity will be carried out. If several
problems are identified, a complete reconfirmation of system integrity shall be
carried out by the Contractor. When reconfirmation has been completed, the 7
day test will be restarted.
- .7 - Any upset of system operational functionality greater than 2 hours during
the 7 day test shall cause the test to be restarted.
- .8 - Printer shall be left on for complete SEVEN (7)-day test. All
printouts will be kept for review at completion of test. An alarm printer shall
be supplied by the Contractor if none is supplied in this contract.
- .9 - Results of all tests shall be documented by the Contractor and submitted through the Landlord to the Consultant and the Corporation for review.
- .10 - System speeds as defined in PS 4.2, PS 5.5, PS 5.7 and PS 5.8 will be tested during the 7-day test.
9.3 - Training and Demonstrations
- The complete training program, (refer to item PS 1.5) shall be carried
out. It may be convenient to schedule this during the 7 day test period.
9.4 - Documentation
- The following documentation must also be in place before completion of
SEVEN (7)-day test and the granting of Substantial Performance:
- .1 - Panel layout sheets complete with point name, point address and wire
identification number. One copy attached to each respective panel door.
- .2 - All points tagged with point name, point address and panel number.
- .3 - System generated data sheets and graphics signed off by both the contractor
and the consultant showing successful commissioning of each point.
- .4 - As-Built control drawings showing interface with existing controls.
- .5 - As-Built ladder wiring diagrams showing all hardware interlocks and panel
input or output number.
- .6 - Complete Operators Manual.
- .7 - Apparatus and Maintenance Manual for all sensors, transducers, valves,
operators, solid state relays, DDC main panels and zone controllers.
- .8 - Graphic plates of floor plans (when provided), showing sensors, terminals, devices, zoning
and stand alone panel locations.
- .9 - Electrical approval certificate.
- .10 - All of the above information, with the exception of #2 (point tags) shall
be bound and presented in TWO (2) manuals to be left on site.
- .11 - A copy of each graphical screen page (when provided), shall be
signed off and dated by the Controls Contractor and the Owner's representative. Any changes shall be noted. This signed set shall be left on
site as the ``as installed drawings''.
- In addition, a summary print out generated by the supplied system of each
group of point types for each panel shall be printed after commissioning and
calibration. Each sheet shall be signed by the Control Contractor's
commissioning person, and the Corporation. The print out
will be stored in a binder on site for reference by all parties. If any
changes are noted during spot checks they shall be manually written on the
original print out with the date and signature of person noting changes.
9.5 - Project Acceptance
- Once the above basic requirements are met and all other features of the
system are complete and acceptable, Substantial Performance shall be granted. A
deficiency list shall be prepared and holdbacks applied. All deficiencies shall
be corrected prior to Total Performance. Warranty shall start from the date of
Substantial Performance of the work.
[
Previous Page ||
Table of Contents ||
Overview ||
Section TOC ||
]
[ Comments
|| Disclaimer ]